Çѱ¹°Ç¼³°ü¸®ÇÐȸ / v.7, no.6, 2006³â, pp.79-89
|
¿öÅÍÁ¬À» ÀÌ¿ëÇÑ ³ë¸éÇ¥½Ã Á¦°ÅÀåºñÀÇ ¼º´ÉÆò°¡¿¡ °üÇÑ ¿¬±¸
( Performance Evaluation of Road Stripe Removing Equipment Using High Pressure Water-Jet ) |
| ÇÑÀ籸;±Ç¼ø¿í;±è±ÕÅÂ; Çѱ¹°Ç¼³±â¼ú¿¬±¸¿ø;¼º±Õ°ü´ëÇб³ °ÇÃà°øÇаú;Çѱ¹°Ç¼³±â¼ú¿¬±¸¿ø;
|
|
|
 |
|
| |
| ÃÊ ·Ï |
| Á¾·¡ÀÇ ±ð±â½Ä Á¦°Å±â¿¡ ÀÇÇÑ ³ë¸éÇ¥½Ã Á¦°ÅÀÛ¾÷Àº Àη¿¡ ÀÇÁ¸ÇÏ´Â ´Ü¼ø¹Ýº¹ ÀÛ¾÷À¸·Î ÁøÇàµÈ´Ù. °æÁ¦»çȸÀûÀÎ Ãø¸é¿¡¼ ÀÌ·¯ÇÑ ¼öÀÛ¾÷Àº ¸Å¿ì ºÒ¸®Çѵ¥, Àå½Ã°£ ±³ÅëÅëÁ¦·Î ÀÎÇÏ¿© ±³ÅëüÁõÀ» ¾ß±â ½Ã۱⠶§¹®ÀÌ´Ù. ÀÌ·¯ÇÑ ±³ÅëüÁõÀº µµ·Î ÀÌ¿ëÀÚÀÇ ºÒÆí°ú È¥Àâºñ¿ëÀÌ Áõ°¡½Ãų »Ó¸¸ ¾Æ´Ï¶ó ±³Åë»ç°íÀÇ °¡´É¼ºµµ °¡Áß½ÃŰ°Ô µÈ´Ù. º» ¿¬±¸ÀÇ ¸ñÀûÀº ¿öÅÍÁ¬ ±â¼úÀ» ÀÌ¿ëÇÑ ³ë¸éÇ¥½Ã Á¦°Å Àåºñ¸¦ °³¹ßÇϰí, °³¹ßÀåºñÀÇ ¼º´ÉÀ» Æò°¡ÇÏ´Â °ÍÀÌ´Ù. ±× °á°ú´Â ´ÙÀ½°ú °°´Ù. ù°, ¿öÅÍÁ¬À» ÀÌ¿ëÇÑ ³ë¸éÇ¥½Ã Á¦°ÅÀåºñ¸¦ °³¹ßÇÏ¿© ÇöÀå½ÇÇèÇÑ °á°ú, ±âÁ¸¹æ½Ä°ú ºñ±³ÇÏ¿© 280.0%ÀÇ »ý»ê¼º ´Þ¼º ºñÀ²À» ¾òÀ» ¼ö ÀÖ¾ú´Ù ¶ÇÇÑ ÆíÀÍ/ºñ¿ë ºñÀ²À» ºÐ¼®ÇÑ °á°ú, ÆíÀÍ/ºñ¿ë ºñÀ²ÀÌ 1º¸´Ù Å« 3.28ÀÌ »êÃâµÇ¾ú´Ù. µû¶ó¼ ³ë¸éÇ¥½ÃÁ¦°Å ÀÚµ¿È Àåºñ¸¦ µµÀÔÇÏ´Â °æ¿ì Ãß°¡ ¼Ò¿äµÇ´Â ºñ¿ëº¸´Ù ¹ß»ýµÇ´Â ÆíÀÍÀÌ ´õ ÅÀ» ¾Ë ¼ö ÀÖ´Ù. µÑ°, °³¹ßÀåºñ·Î ±âÁ¸ ¹æ½ÄÀÇ 190ÀÏ ÀÛ¾÷¹°·®À» ÀÛ¾÷ÇÒ °æ¿ì, Àåºñ ÇѴ븶´Ù ¿¬°£ ¾à 25.5¾ï¿øÀÇ ±³ÅëÈ¥Àâºñ¿ëÀ» Àý°¨ÇÒ ¼ö ÀÖÀ½À» ¾Ë ¼ö ÀÖ¾ú´Ù µû¶ó¼ ³ë¸éÇ¥½ÃÁ¦°Å ¾÷üµéÀÌ º» ¿¬±¸ÀÇ °³¹ßÀåºñ¸¦ µµÀÔÇÔÀ¸·Î½á ¾òÀ» ¼ö ÀÖ´Â »çȸÀû ÆíÀÍÀº ¸·´ëÇÒ °ÍÀ¸·Î ±â´ëµÈ´Ù. |
|
| Current removing process is labor intensive and time consuming, employing a conventional grinding type manual machine. From a social and economic point of views, these kinds of manual tasks bring about social inconvenience and economic loss including traffic jam and high labor costs. The objective of the study was to develop and evaluate a road stripe removal equipment using water jet technology. The following shows the results. First, It was analyzed that the obtainable productivity from the equipment developed in the study is 280% compared to the current equipment. In this study, it was also calculated the Benefit/Cost Ratio and the result showed that the ratio is 3.28, so it is expected that the equipment can produce great benefits for the relevant companies. Second, an analysis was also conducted on the traffic congestion cost, and the equipment could save about 2,550 million per day compared to the conventional equipment. Therefore, it is analyzed that the economic viability of the equipment is sufficient. |
| |
| Ű¿öµå |
| Ãʰí¾Ð¼ö;³ë¸éÇ¥½Ã;°Ç¼³ÀÚµ¿È;¾ÈÀü;¼º´ÉÆò°¡;water-jet;road stripes;construction automation;work process analysis;safety;performance evaluation; |
| |
|
|
 |
|
Çѱ¹°Ç¼³°ü¸®ÇÐȸ³í¹®Áý / v.7, no.6, 2006³â, pp.79-89
Çѱ¹°Ç¼³°ü¸®ÇÐȸ
ISSN : 2005-6095
UCI : G100:I100-KOI(KISTI1.1003/JNL.JAKO200634515089924)
¾ð¾î : Çѱ¹¾î |
|
| ³í¹® Á¦°ø : KISTI Çѱ¹°úÇбâ¼úÁ¤º¸¿¬±¸¿ø |
|
|
|
|
|
|