Çѱ¹°Ç¼³°ü¸®ÇÐȸ / v.4, no.3, 2003³â, pp.128-136
|
»ç·Ê ºÐ¼®À» ÅëÇÑ ÅÏŰ ÇÁ·ÎÁ§Æ® ½Ç½Ã¼³°è ¾÷¹« °ü¸®¹æ¾È
( Design Development Management in the Design-Build Project by Cast-Study ) |
| ÀÌȲ±¸;±è¿µÀç;±è°æ·¡;¹ÚÂù½Ä;½Åµ¿¿ì; ¾ÆÁÖ´ëÇб³ °ÇÃàÇкÎ;¾ÆÁÖ´ëÇб³ °ÇÃàÇкÎ;¾ÆÁÖ´ëÇб³ °ÇÃàÇкÎ;Áß¾Ó´ëÇб³ °ÇÃàÇаú;¾ÆÁÖ´ëÇб³ °ÇÃàÇкÎ;
|
|
|
 |
|
| |
| ÃÊ ·Ï |
| ÅÏ۰ø»çÀÇ ¾÷¹«¼öÇàü°è´Â ±âº»¼³°è, ÀÔÂû, ³«Âû, ½Ç½Ã¼³°è, °è¾à, ½Ã°ø, »ç¾÷¹° Àεµ¿Í °°Àº ÀýÂ÷·Î ±¸¼ºµÇ¾î ÀÖ´Ù. ÅÏŰ¹ßÁÖ °ø»çÀÇ ÇÁ·Î¼¼½º Áß ÀÌ·¯ÇÑ ¼³°è¾÷¹«´Â Àϰý°è¾àÀÚÀÎ ±âÁ¸ÀÇ °Ç¼³È¸»ç¿¡¼ ´ã´çÇÏÁö ¾ÊÀº »ý¼ÒÇÑ ºÎºÐÀÇ ¾÷¹«ÀÌ´Ù ÀÌ Áß ½Ç½Ã¼³°è Àû°ÝÀÚ ¼±Á¤ÀÌÈĴܰ迡¼ °è¾à´Ü°è±îÁöÀÇ °úÁ¤¿¡ ÇØ´çÇÏ´Â ½Ç½Ã¼³°è´Ü°è¿¡´Â »ç¾÷³»¿ë¿¡ ´ëÇÑ ±¸Ã¼ÀûÀÎ Á¶Á¤ ¹× ÃÖÁ¾°áÁ¤°ú °ü·ÃµÈ ¾÷¹«°¡ Á¸ÀçÇϹǷΠ»ç¾÷¼ºÆÐ¿¡ »ó´çÈ÷ Áß¿äÇÑ ´Ü°è·Î ¿©°ÜÁö°í ÀÖÀ¸³ª, ±âÁ¸ÀÇ ½Ã°ø´Ü°èÀÇ °ü¸®¾÷¹«¸¸À» ¼öÇàÇÏ´ø Àϰý »ç¾÷ÀÚ¿¡°Ô´Â Çö½ÇÀûÀ¸·Î ´Ù¼Ò »ý¼ÒÇÑ ¾÷¹«ºÐ¾ßÀÌ´Ù ÇöÀç ±¹³» ÅÏ۰ø»ç¿¡¼´Â ½Ç½Ã¼³°è´Ü°è¿¡ ´ëÇÑ Ã¼°èÀûÀÌÁö ¸øÇÑ ¾÷¹«°ü¸®·Î ÀÎÇØ ¼³°èº¯°æ ¿äû, Ŭ·¹ÀÓ Á¦±â µîÀÌ ¹ß»ýÇϰí ÀÖ´Ù. ÀÌ·¯ÇÑ ¿øÀÎÀº ÅÏ۰ø»ç¶ó´Â ½Ç½Ã¼³°è¾÷¹«¿¡ ´ëÇÑ ±¸Ã¼Àû ¹®Á¦Á¡ Àνİú ÀÌ¿¡ ´ëÇÑ °ü¸®¹æ¾ÈÀÌ Ã¼°èȵǾî ÀÖÁö ¸øÇÔ¿¡ ±âÀÎÇÑ´Ù. µû¶ó¼ º» ¿¬±¸¿¡¼´Â ÅÏŰ¼öÇà°ø»ç ±âÁ¸ ¼³°è½Ã°ø Àϰý»ç¾÷ °ü·Ã¹®Çå ¹× ¼±Çà ¿¬±¸°íÂûÀ» ÅëÇÑ »ç·ÊÁ¶»ç¿¬±¸¸¦ ¼³°èÇϰí À̸¦ Åä´ë·Î ÇöÀç °ø»ç ÁßÀÎ ÇöÀå¿¡ ´ëÇÑ »ç·ÊÁ¶»ç¸¦ ¼öÇàÇÏ¿´´Ù. »ç·ÊÁ¶»ç ³»¿ëÀ» ºÐ¼®ÇÔÀ¸·Î½á ÇöÇà ÅÏ۰ø»çÀÇ ½Ç½Ã¼³°è ÁÖ¿ä °ü¸®¾÷¹« ¹× ¼öÇà»óÀÇ ¹®Á¦Á¡À» ±¸Ã¼ÈÇÏ¿´À¸¸ç, ½ÇÁ¦ ½Ç½Ã¼³°è °ü¸®¾÷¹« ´ã´çÀÚµéÀÇ °³¼±¹æÇâ¿¡ ÀǰßÀ» Á¤¸®Çϰí À̸¦ ÅëÇÑ ½Ç½Ã¼³°è °ü¸®¾÷¹«¿¡ ´ëÇÑ °³¼±¹æ¾ÈÀ» Á¦½ÃÇÏ¿´´Ù. |
|
| The contractors which execute the design-build project have difficulties in design management and contract administration in the pre-construction phase because they have managed construction projects focused on only construction phase so far. Moreover, they have to manage the design development stage without any contingency following-up various design revisions from the design reviews of outside experts. Therefore, the design management in the design development stage is a critical success facto. of the design-build project. The objective of this study is to structure the problems in the management skill for design development phase in the domestic design-build projects and to suggest a design development management method to settle the problems. To achieve these objectives, this study 1) analyzes the prior studies about the design-build procurement methods, 2) designs and performs a case study to embody the problems of the domestic design-build projects, and 3) proposes a method of design development management by analyzing the results of case study and interviewing experts. |
| |
| Ű¿öµå |
| ÅÏŰ ÇÁ·ÎÁ§Æ®;½Ç½Ã¼³°è °ü¸®;ÁÖ¿ä °ü¸® ¾÷¹«;»ç·ÊÁ¶»ç;Design-Build Project;Design Development Management;Case Study; |
| |
|
|
 |
|
Çѱ¹°Ç¼³°ü¸®ÇÐȸ³í¹®Áý / v.4, no.3, 2003³â, pp.128-136
Çѱ¹°Ç¼³°ü¸®ÇÐȸ
ISSN : 2005-6095
UCI : G100:I100-KOI(KISTI1.1003/JNL.JAKO200320828322094)
¾ð¾î : Çѱ¹¾î |
|
| ³í¹® Á¦°ø : KISTI Çѱ¹°úÇбâ¼úÁ¤º¸¿¬±¸¿ø |
|
|
|
|
|
|